2016 (Jira - Khonkaen)
Provide - Cable Detector.
Provide - Railway Equipment.
2020 - 2023
Signailing & Telecom Construction Supervision Lop Buri to Pac Nam Po
2021
ITDRT - Double Track Contract 3
Mab Kabao - Chira
Trackworks Installation.
2021
ITD Double Track Mab Kabao - Chira Contact 1
Trackworks, Turnout Installation.
2022
ITDRT Double Track Mab Kabao - Chira Contract 3
Trackworks, Turnout Installation.
The steps for carrying out the project are as follows :

Step 1 Spread the rail sleepers.

Step 2 Assemble the fastner.

Step 3 Tie iron + uo the rails sleepers.

Step 4 Install rails up the sleepers.

Step 5 Tie iron + spread sleepers.

Step 6 Tie iron + Lifting rail sleepers.

Step 7 Tie iron + upthe rails + upthe sleepers.

Step 8 Pour cement